Skip to content

Varanasi To Get 89-Km Elevated Corridors Along Ganga And Varuna

Varanasis Elevated Ganga Corridors

The National Highways Authority of India is developing 89.2 km of elevated corridors along the Ganga and Varuna rivers to significantly reduce travel times and improve connectivity in Varanasi.

Key Points

  • Project Scope: Two major corridors totaling 89.2 km will be constructed along the Ganga and Varuna rivers.
  • Bid Response: The NHAI received a total of 32 bids for the four development packages across both projects.
  • Varuna Corridor: The 43.2-km Varuna project will cost ₹10,998.32 crore and connect NH-31 with the Varanasi Ring Road.
  • Ganga Corridor: The 46-km Ganga project will cost ₹14,447.64 crore and connect NH-19 with the Varanasi Ring Road.
  • Travel Impact: The corridors aim to reduce travel times from 40 to 20 minutes for the Varuna route and 60 to 20 minutes for the Ganga route.

Major Infrastructure Boost For Varanasi

VARANASI: The National Highways Authority of India (NHAI) is set to develop two massive elevated corridor projects along the Rivers Ganga and Varuna in Uttar Pradesh. These projects, which span a combined length of approximately 89.2 km, are designed to alleviate severe traffic congestion and provide seamless connectivity to the city’s primary religious, cultural, and transport hubs.

The projects were officially approved by the Cabinet Committee on Economic Affairs (CCEA) in July 2026. According to the NHAI, the initiative has seen a strong response from the private sector, with 32 bids received for the four development packages. The Varuna Elevated Corridor will be split into two packages, while the Ganga Elevated Corridor will also be developed in two separate packages under the Hybrid Annuity Model (HAM).

Varuna Corridor Connectivity Details

The Varuna Elevated Corridor, measuring 43.2 km in length, will connect NH-31 with the Varanasi Ring Road. This project carries a total capital cost of ₹10,998.32 crore. It will feature an elevated 6/4-lane corridor, including the main carriageway, flyovers, loops, ramps, and service roads. The infrastructure is designed for operating speeds between 80 and 100 kmph.

This corridor is expected to be a game changer for local transit, reducing the travel time between NH-31 and Kashi Railway Station from 40 minutes to just 20 minutes. It will provide enhanced access to the Varanasi Airport, Varanasi Junction, Deen Dayal Upadhyaya Junction, and the city’s famous ghats. Furthermore, it will strengthen regional ties by improving access to the Chandauli region and six major logistics nodes.

Ganga Corridor And Economic Impact

The Ganga Elevated Corridor will span 46 km and connect NH-19 with the Varanasi Ring Road. With a capital cost of ₹14,447.64 crore, this six-lane project will include a 910-metre cable-stayed bridge and a 1.32-km extradosed Foot Over Bridge-cum-Major Bridge. The corridor is intended to slash average travel times from 60 minutes down to 20 minutes along the riverfront.

Beyond improving access to the Kashi Vishwanath Temple, Banaras Hindu University (BHU), and Namo Ghat, the project aligns with the PM Gati Shakti National Master Plan. It aims to facilitate the movement of industrial goods, construction materials, and agricultural produce, thereby supporting economic growth across eastern Uttar Pradesh. The journey between NH-19 and Kashi Railway Station is also projected to drop from 50 minutes to 25 minutes.

Bidding Process And Development

The NHAI reported that the Varuna Elevated Corridor attracted eight bids for Package I and seven for Package II. The Ganga Elevated Corridor saw even higher interest, with eight bids for Package I and nine for Package II. These figures indicate significant developer interest in the ₹25,446 crore total investment for the Varanasi region.

By integrating multimodal transport and improving access to the Ramnagar Port and Lal Bahadur Shastri Airport, the corridors are expected to reduce vehicle operating costs. The construction will focus on providing high-speed, access-controlled connectivity that serves both the spiritual tourism sector and the industrial requirements of the state.

Read next